Question: Chapter 6 , Question 4 Given the following production schedule, compute the available - to - promise quantities. Week 1 2 3 4 5 6

Chapter 6, Question 4
Given the following production schedule, compute the available-to-promise quantities.
Week
1
2
3
4
5
6
7
8
MPS BI=60
20
30
20
20
20
50
0
20
Cust. Orders
50
10
30
10
20
20
10
0
ATP
Q1a
HomeworkUnansweredDue Today, 11:00 PM
What is the discrete ATP in period 2?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
Unanswered2 attempts left
Submit
Please answer to submit
Q1b
HomeworkUnansweredDue Today, 11:00 PM
What is the discrete ATP in period 6?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
Unanswered2 attempts left
Submit
Please answer to submit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!