Question: Chen is conducting a case study for statistical process control for her business. She has performed a 10-week study with 315 samples done each week
Chen is conducting a case study for statistical process control for her business. She has performed a 10-week study with 315 samples done each week and has calculated the average p to be .045. She wants to know the highest number before her process is out of control