Question: choose the correct answer 1)The order quantity Y1(plastic cups) is * a-1208.77 unit b-None of the answers. c-1702.55 unit d-1802.77 unit e-1708.22 unit === 2)The

choose the correct answer
1)The order quantity Y1(plastic cups) is * a-1208.77 unit b-None of the answers. c-1702.55 unit d-1802.77 unit e-1708.22 unit
=== 2)The order quantity Y2(box) = * a-163.72 unit b-None of the answers. c-316.23 unit d-363.13 unit e-613.83 unit
==== 3)( ) equals * a-564.64 b-456.46 c-645.61 d-None of the answers. e-546.46
=== 4)applying the constraint ( ) , and taking into account that A=550 m2, we deduce that _____ and _____. * a-the constraint is violated & binding; must be accounted for b-None of the answers. c-the constraint is satisfied; Y(1) & Y(2) are optimal. d-the constraint is violated; Y(1) & Y(2) are optimal. e-the constraint is satisfied; Y(1) & Y(2) are not optimal.
=== 5)Total Cost per unit equals * a-TCU (Y1*) + TCU (Y2*) = $478.79 b-TCU (Y1*) + TCU (Y2*) = $5977.54 c-TCU (Y1*) + TCU (Y2*) = $9577.54 d-TCU (Y1*) + TCU (Y2*) = $978.74 e-None of the answers
A company needs about 325,000 butter packs per month. Each butter order costs $15. The holding cost of one butter pack equals 1/5 cost per order. The order is supplied at the same day of the order. One butter takes 0.04m of space. In addition, the company needs 7,500 bags of flour per month. Each flour order costs $12. The holding cost of one flour bag equals 15% of the cost per order. The order is supplied at the same day of the order. One flour bag takes 1.5m? of space. The company has a 550m2 storage spaceStep by Step Solution
There are 3 Steps involved in it