Question: Choose the correct answer based on the table provided: 1. Assume your BAC for the project is R2 000 000. Your VAC at the end

Choose the correct answer based on the table provided:

1. Assume your BAC for the project is R2 000 000. Your VAC at the end of week 6, using EACf, and assuming your efficiency decreases by a quarter, suggests that you will be (round all workings to two decimal places):

B.R212 500 under budget at the end of the project

A. R200 000 under budget at the end of the project

C. R229 110 over budget at the end of the project

D. R212 500 over budget at the end of the project

2. Assume your BAC is R2 000 000. Your PCIC at the end of week 6, which you calculated using EACf, having assumed that your revised efficiency as calculated in question 4 has now increased by 10%, suggests that you are (rounded to two decimal places):

A. 41% complete in terms of budget

D. 43% complete in terms of cost

C. 43% complete in terms of budget

B. 41% complete in terms of cost

Choose the correct answer based on the table

mo Task % Complete EV AC PV CV SV A 100% 100 200 100 B 100% 250 200 250 100% 450 400 450 D 75% 150 100 100 Cumulative Totals 950 900 900 Table 2 - Status report at the end of Time Period 6 (in 000's)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock