Question: Task % Complete EV AC PV CV SV 1 Finish 2000 1500 2000 2 Finish 2400 2000 2400 3 50% 1500 800 2000 4 60%

Task

% Complete

EV

AC

PV

CV

SV

1

Finish

2000

1500

2000

2

Finish

2400

2000

2400

3

50%

1500

800

2000

4

60%

1500

1500

2200

5

25%

400

400

400

Cumulative totals

Table 2 Status Report at the end of Week 5 (in R000s)

Equations: CV = EV AC; SV = EV PV; CPI = EV/AC; SPI = EV/PV; PCIC = AC/EACf; PCIB = EV/BAC; VAC = BAC EACf; EACf is computed as follows: ETC + AC where ETC is (BAC EV) CPI; SVt = ES-AT; SPIt= ES/AT; ETCt= (PD-ES)/SPIt

Complete the status report on separate piece of paper and answer questions 18 - 25.

Please select the answers from group of answers given

Question 1

With reference to your completed status report, the Cost Variance at the end of week 5 suggests that:

Group of answer choices

R1 600 000 ahead of schedule

R1 600 000 under budget

R1 600 000 over budget

R1 600 000 behind schedule

Question 2

Refer to the Status Report at the end of week 5 you completed in question 1.

The Cost Performance index at the end of week 5 (rounded to two decimal points) indicates that:

Group of answer choices

For every R1 planned you have accomplished an extra 26c worth of work indicating you are ahead of schedule and very efficient

For every R1 spent you have accomplished an extra 26c worth of work indicating you are behind schedule and very inefficient

For every R1 spent you have accomplished an extra 26c worth of work indicating you are under budget and very efficient

For every R1 planned you have accomplished an extra 26c worth of work indicating you are under budget and inefficient

Question 3

Refer to the Status Report at the end of week 5 you completed in question 1.

The Schedule Variance at the end of week 5 (rounded to two decimal points) suggests that:

Group of answer choices

The project is R1 200 000 over budget

The project is R1 200 000 ahead of schedule

The project is R1 200 000 under budget

The project is R1 200 000 behind schedule

Question 4

Refer to the Status Report at the end of week 5 you completed in question 1.

The Schedule Performance index at the end of week 5 (rounded to two decimal points) indicates that:

Group of answer choices

For every R1 planned you have accomplished 87c worth of work indicating you are behind schedule and inefficient

For every R1 spent you have accomplished 87c worth of work indicating you are over budget and inefficient

For every R1 planned you have accomplished 87c worth of work indicating you are ahead of schedule and very efficient

For every R1 spent you have accomplished 87c worth of work indicating you are behind schedule and inefficient

Question 5

Refer to the Status Report at the end of week 5 you completed in question 1.

Assume your BAC is R14 500 000, the PCIB (rounded to two decimal places) suggests that you are:

Group of answer choices

5.40% complete in terms of budget

54% complete in terms of budget

60% complete in terms of budget

54% complete in terms of cost

Question 6

Refer to the Status Report at the end of week 5 you completed in question 1.

Assume your BAC is R14 500 000. Your PCIC at the end of week 5, which you calculated using EACf, having assumed that your efficiency has increased by 30%, suggests that you are (rounded all workings to two decimal places):

Group of answer choices

54% complete in terms of cost

54% in terms of budget

60% complete in terms of cost

60% complete in terms of budget

Question 7

Refer to the Status Report at the end of week 5 you completed in question 1.

Assume your BAC is R14 500 000. If your revised efficiency changes to 200% as opposed to remaining at the same level as calculated in question 6, your VAC at the end of week 5, which you calculated using EACf, suggests that you will now be (round all workings to two decimal places):

Group of answer choices

R4 214 630 under budget at the end of the project

An additional R735 370 under budget the end of the project

R4 950 000 over budget at the end of the project

An additional R735 370 over budget at the end of the project

Question 8

Based on the performance of the project at the end of week 5, your likely assessment and recommendation would be most likely be that:

Group of answer choices

Based on schedule variance alone, the project is performing adequately, and there is no need to intervene at this stage.

The current cost variance in conjunction with the CPI indicate significant under-performance on the part of the project team and project team leadership.

Based on current overall performance, it is likely that even at a relatively early stage, premature closure of the project is strongly recommended as the organisation has categorically stated it cannot absorb excessive cost and schedule overruns.

With some intervention, and if the project continues on its current trajectory, then the project will likely come in on budget, and potentially on schedule given that it is at a relatively early stage.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!