Question: CLASS ACTIVITY-SUBMIT IN MOODLE Given the information in the following table: Assume the Project commences on the 8th Day Activity Immediate Time (Days) Predecessor(s) 1.

CLASS ACTIVITY-SUBMIT IN MOODLE Given the
CLASS ACTIVITY-SUBMIT IN MOODLE Given the information in the following table: Assume the Project commences on the 8th Day Activity Immediate Time (Days) Predecessor(s) 1. Construct the network diagram using AON A 2 2. Find the activity's ES, EF, LS and LF. B 5 C 1 3. Identify all paths. D B 10 4. Which path is the critical path? A.D 3 5. Calculate the slack for each activity F C 6 6. How long will it take to complete the project? G E,F 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer