Question: Construct the network diagram. b. Find each activity's EST, EFT, LST, and LFT. c. Identify all paths. Which pach is the critical path? d. Calculate


Construct the network diagram. b. Find each activity's EST, EFT, LST, and LFT. c. Identify all paths. Which pach is the critical path? d. Calculate the slack for cach activity. e. How long will it take to complete the project? 26. Given the information in the following table, draw the AOA network. Using the same information, enter the data into MSP assuming a seven-day workweek. (To change the calendar in MSP from its five-day week default click "Help, type "calendar change," and follow directions.) Develop the appropriate AON net- work and Gantt chart. Using any method you wish,find the critical path and critical time for the network, Then find the slack for all activities. Activity Predecessor Duration 5 days d. e d. c f, g, h