Question: CLASS EXERCISE | PROJECT CONTROL / PROJECT ACCELERATION Calculate the least cost and crash duration for the following project. Calculate the cost associated with each

CLASS EXERCISE| PROJECT CONTROL / PROJECT ACCELERATION
Calculate the least cost and crash duration for the following project. Calculate the cost associated with each duration. Indirect costs are $100 per day. Draw the network diagram and perform forward and backward calculation. (Network Diagram -5 points, Complete Crashing Table -15 points)
\table[[ACTIVITY,IPA,DURATION,COSTS],[NORMAL,CRASH,NORMAL,CRASH],[A,-,7,5,$500,640],[B,A,6,5,550,630],[C,A,8,5,800,935],[D,B,10,7,1,200,1,440],[E,B,C,6,4,600,700],[F,C,4,3,500,590],[G,D,F,4,2,700,1,000],[H,E,F,7,4,650,950],[I,G,H,2,2,300,300]]
Note: Draw the network diagram below and use the attached table for the calculation.
CLASS EXERCISE | PROJECT CONTROL / PROJECT

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!