Question: Clients are served in a process with two resources. The processing time of the first resource is 1 1 hours. The processing time of the

Clients are served in a process with two resources. The processing time of the first resource is 11 hours. The processing time of the second resource is 12 hours. The first resource has 4 worker and the second resource has 3 workers. The cycle time of the process is 18 hours.
Instruction: Round your answer to one decimal place.
What is the average labor utilization (%)? percent