Question: Clients are served in a process with two resources. The processing time of the first resource is 6 hours. The processing time of the second
Clients are served in a process with two resources. The processing time of the first resource is 6 hours. The processing time of the second resource is 8 hours. The first resource has 2 workers and the second resource has 8 workers. The cycle time of the process is 15 hours.
Round your answer to one decimal place.
What is the average labor utilization (%)?