Question: Clients are served in a process with two sequential resources. The capacities of the resources are 1 7 and 4 5 clients per hour. What

Clients are served in a process with two sequential resources. The capacities of the resources are 17 and 45 clients per hour. What is the capacity of this process in terms of clients per hour