Question: Compare the options below using a present worth analysis and an interest rate of 8% per year. Calculate the PW for Machine X. Calculate the
Compare the options below using a present worth analysis and an interest rate of 8% per year.
Calculate the PW for Machine X.
Calculate the PW for Machine Y.

Mach X $500,000 $8000 $25,000 Mach Y 300,000 $6000 Initial cost Annual operating cost Overhaul every 10 years Salvage value Life (years) 8.00% 8.00% n F/P P/F A/F A/P FIA PIA AIG P/G 1 1.0800 0.9259 1.0000 1.0800 1.0000 0.9259 0.0000 0.0000 2 1.1664 0.8573 0.4808 0.5608 2.0800 1.7833 0.4808 0.8573 3 1.2597 0.7938 0.3080 0.3880 3.2464 2.5771 0.9487 2.4450 4 1.3605 0.7350 0.2219 0.3019 4.5061 3.3121 1.4040 4.6501 5 1.4693 0.6806 0.1705 0.2505 5.8666 3.9927 1.8465 7.3724 6 1.5869 0.6302 0.1363 0.2163 7.3359 4.6229 2.2763 10.5233 7 1.7138 0.5835 0.1121 0.1921 8.9228 5.2064 2.6937 14.0242 8 1.8509 0.5403 0.0940 0.1740 10.6366 5.7466 3.0985 17.8061 9 1.9990 0.5002 0.0801 0.1601 12.4876 6.2469 3.4910 21.8081 10 2.1589 0.4632 0.0690 0.1490 14.4866 6.7101 3.8713 25.9768 $75,000 8 OO
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts