Question: Complete Case outline on Arctic Mining Consultants 1) Problem Statement -One to two sentences -What is the basic problem? -Why is this a case ?
Complete Case outline on Arctic Mining Consultants
1) Problem Statement -One to two sentences -What is the basic problem? -Why is this a case ?
2) Problem Analysis -Why do the problems exist? -Use concept/theories from text. -Strengths & Weaknesses -Internal -Company-level -Example: corporate culture
3) Recommendation -Based on your analysis and topics from the text, what would your group do to solve the problem
CASE 2: ARCTIC MINING CONSULTANTS
By Steven L. McShane, Curtin University (Australia) and University of Victoria (Canada);
and Tim Neale
Tom Parker enjoyed working outdoors. At various times in
the past, he worked as a ranch hand, high steel rigger,
headstone installer, prospector, and geological field technician.
Now 43, Parker is a geological field technician and
field coordinator with Arctic Mining Consultants. He has
specialized knowledge and experience in all nontechnical
aspects of mineral exploration, including claim staking,
line cutting and grid installation, soil sampling, prospecting,
and trenching. He is responsible for hiring, training,
and supervising field assistants for all of Arctic Mining
Consultants' programs. Field assistants are paid a fairly
low daily wage (no matter how long they work, which may
be up to 12 hours or more) and are provided meals and accommodation.
Many of the programs are operated by a
project manager who reports to Parker.
Parker sometimes acts as a project manager, as he did
on a job that involved staking 15 claims near Eagle Lake,
Alaska. He selected John Talbot, Greg Boyce, and Brian
Millar, all of whom had previously worked with Parker, as
the field assistants. To stake a claim, the project team
marks a line with flagging tape and blazes along the perimeter
of the claim, cutting a claim post every 500 yards
(called a "length"). The 15 claims would require almost
60 miles of line in total. Parker had budgeted seven days
(plus mobilization and demobilization) to complete the
job. This meant that each of the four stakers (Parker, Talbot,
Boyce, and Millar) would have to complete little
over seven "lengths" each day. The following is a chronology
of the project.
DAY 1
The Arctic Mining Consultants crew assembled in the
morning and drove to Eagle Lake, from where they were
flown by helicopter to the claim site. On arrival, they set
up tents at the edge of the area to be staked, and agreed on
a schedule for cooking duties. After supper, they pulled out
the maps and discussed the jobhow long it would take,
the order in which the areas were to be staked, possible
helicopter landing spots, and areas that might be more
difficult
to stake.
Parker pointed out that with only a week to complete
the job, everyone would have to average seven and a half
lengths per day. "I know that is a lot," he said, "but you've
all staked claims before and I'm confident that each of you
is capable of it. And it's only for a week. If we get the job
done in time, there's a $300 bonus for each man." Two
hours later, Parker and his crew members had developed
what seemed to be a workable plan.
DAY 2
Millar completed six lengths, Boyce six lengths, Talbot
eight, and Parker eight. Parker was not pleased with Millar's
or Boyce's production. However, he didn't make an
issue of it, thinking that they would develop their "rhythm"
quickly.
DAY 3
Millar completed five and a half lengths, Boyce four, and
Talbot seven. Parker, who was nearly twice as old as the
other three, completed eight lengths. He also had enough
time remaining to walk over and check the quality of stakes
that Millar and Boyce had completed, then walk back to his
own area for helicopter pickup back to the tent site.
That night Parker exploded with anger. "I thought I told
you that I wanted seven and a half lengths a day!" he
shouted at Boyce and Millar. Boyce said that he was slowed
down by unusually thick underbrush in his assigned area.
Millar said that he had done his best and would try to pick
up the pace. Parker did not mention that he had inspected
their work. He explained that as far as he was concerned,
the field assistants were supposed to finish their assigned
area for the day, no matter what.
Talbot, who was sharing a tent with Parker, talked to
him later. "I think that you're being a bit hard on them, you
know. I know that it has been more by luck than anything
else that I've been able to do quota. Yesterday I only
had five lengths done after the first seven hours and there
was only an hour before I was supposed to be picked up.
Then I hit a patch of really open bush, and was able to do
three lengths in 70 minutes. Why don't I take Millar's area
tomorrow and he can have mine? Maybe that will help."
"Conditions are the same in all of the areas," replied Parker,
rejecting Talbot's suggestion. "Millar just has to try harder."
DAY 4
Millar did seven lengths and Boyce completed six and a
half. When they reported their production that evening,
Parker grunted uncommunicatively. Parker and Talbot did
eight lengths each.
DAY 5
Millar completed six lengths, Boyce six, Talbot seven and
a half, and Parker eight. Once again Parker blew up, but he
concentrated his diatribe on Millar. "Why don't you do
what you say you are going to do? You know that you have
to do seven and a half lengths a day. We went over that
when we first got here, so why don't you do it? If you
aren't willing to do the job then you never should have
taken it in the first place!"
Millar replied by saying that he was doing his best, that
he hadn't even stopped for lunch, and that he didn't know
how he could possibly do any better. Parker launched into
him again: "You have got to work harder! If you put
enough effort into it, you will get the area done!"
Later Millar commented to Boyce, "I hate getting dumped
on all the time! I'd quit if it didn't mean that I'd have to walk
50 miles to the highway. And besides, I need the bonus
money. Why doesn't he pick on you? You don't get any more
done than me; in fact, you usually get less. Maybe if you did
a bit more he wouldn't be so bothered about me."
"I only work as hard as I have to," Boyce replied.
DAY 6
Millar raced through breakfast, was the first one to be
dropped off by the helicopter, and arranged to be the
last one picked up. That evening the production figures
were Millar eight and a quarter lengths, Boyce seven,
and Talbot and Parker eight each. Parker remained silent
when the field assistants reported their performance
for the day.
DAY 7
Millar was again the first out and last in. That night, he collapsed
in an exhausted heap at the table, too tired to eat.
After a few moments, he announced in an abject tone, "Six
lengths. I worked like a dog all day and I only got a lousy
six lengths!" Boyce completed five lengths, Talbot seven,
and Parker seven and a quarter.
Parker was furious. "That means we have to do a total
of 34 lengths tomorrow if we are to finish this job on
time!" With his eyes directed at Millar, he added: "Why is
it that you never finish the job? Don't you realize that you
are part of a team, and that you are letting the rest of the
team down? I've been checking your lines and you're doing
too much blazing and wasting too much time making
picture-perfect claim posts! If you worked smarter, you'd
get a lot more done!"
DAY 8
Parker cooked breakfast in the dark. The helicopter dropoffs
began as soon as morning light appeared on the horizon.
Parker instructed each assistant to complete eight
lengths and, if they finished early, to help the others. Parker
said that he would finish the other 10 lengths. Helicopter
pickups were arranged for one hour before dark.
By noon, after working as hard as he could, Millar had
only completed three lengths. "Why bother," he thought to
himself, "I'll never be able to do another five lengths before
the helicopter comes, and I'll catch the same amount
of abuse from Parker for doing six lengths as for seven and
a half." So he sat down and had lunch and a rest. "Boyce
won't finish his eight lengths either, so even if I did finish
mine, I still wouldn't get the bonus. At least I'll get one
more day's pay this way."
That night, Parker was livid when Millar reported that
he had completed five and a half lengths. Parker had done
ten and a quarter length, and Talbot had completed eight.
Boyce proudly announced that he finished seven and a half
lengths, but sheepishly added that Talbot had helped him
with some of it. All that remained were the two and a half
lengths that Millar had not completed.
The job was finished the next morning and the crew demobilized.
Millar has never worked for Arctic Mining
Consultants again, despite being offered work several
times by Parker. Boyce sometimes does staking for Arctic,
and Talbot works full time with the company.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
