Question: Complete Problem 11.16 (page 414 in your text book) Consider the following activities and their durations. Activity Duration A 5 days B 30 days C

Complete Problem 11.16 (page 414 in your text book) Consider the following activities and their durations. Activity Duration A 5 days B 30 days C 10 days D 10 days E 15 days Figure 11.20 The original project schedule, using early activity starts, is shown in the diagram below. Figure 11.20 Answer the following questions: What is the critical path? How much slack is currently available in the non-critical path? Reconfigure the network in Figure 11.20 as a critical chain network. What is the new duration of the project? How long are the project and feeder buffers