Question: Complete SV , CV , CPI, SPI and EAC for each week. Also, plot plot CPI and SPI over time. BAC = 4 6 0

Complete SV, CV, CPI, SPI and EAC for each week. Also, plot plot CPI and SPI over time.
BAC =460
Week
BCWS
BCWP
ACWP
SV
CV
CPI
SPI
EAC
1
50
50
35
2
70
60
40
3
90
80
67
4
120
105
90
5
130
120
115
6
140
135
130
7
165
150
155
8
200
175
190
9
250
220
230
10
270
260
270
11
300
295
305
12
350
340
340
13
380
360
370
14
420
395
400
15
460
460
450