Question: Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $140,000.

Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $140,000. Earned value data is available for the first three weeks of the project (see below). The project is due to end on week 4.

Project Data

Week 1

Week 2

Week 3

Week 4

Cumulative Actual Costs

$2,700

$15,700

$37,800

Anticipated planned Value

$11,750

$22,000

$43,000

$64,000

Cumulative Earned value

$6,750

$21,500

$47,000

Based on the above data, calculate the following earned value indicators:

EVM Indicator

Week 1

Week 2

Week 3

Formula used

Cost Variance

Schedule Variance

Cost Performance Index

Schedule Performance Index

Estimated Cost At Completion

(use the EAC = BAC / CPI formula)

Estimated Cost to Complete

For this question you need to:

  • Identify which formulas you used for each indicator;
  • Show an example of your calculations (work) for each indicator; and

Calculate each indicator for each of the first three weeks

Question 3:

  • Based on the question 2 data, represent the projects earned value status in a visual format.
  • Your image need only include your AC, EV, and PV over the four-week project (see example chart at right).
  • This chart can be done in Excel (or equivalent), or it can be drawn by hand (and then digitally scanned or photographed, and included in your assignment).

Question 4: Interpret the Projects Status

Using the SV, CV, CPI, SPI, EAC and ETC values that you calculated in question 2 along with your earned value dashboard that you prepared in question 3, provide a descriptive analysis and interpretation of the projects status.

Answers the following questions:

  • At week three, is the project on-budget? (Or over? Or under?)

How does this compare to week one?

  • At week three, is the project on-schedule? (Or behind? Or ahead?)

How does this compare to week one?

  • Are the projects cost and schedule performances improving over time? Or worsening?
  • From week one to week three, has the estimated completion cost gone up? Or down?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!