Question: Complete SV, CV, CPI, SPI and EAC for each week. Also, plot plot CPI and SPI over time. BAC = 460 Week BCWS BCWP ACWP
Complete SV, CV, CPI, SPI and EAC for each week. Also, plot plot CPI and SPI over time.
BAC = 460
Week | BCWS | BCWP | ACWP | SV | CV | CPI | SPI | EAC |
1 | 50 | 50 | 25 |
|
|
|
|
|
2 | 70 | 60 | 40 |
|
|
|
|
|
3 | 90 | 80 | 67 |
|
|
|
|
|
4 | 120 | 105 | 90 |
|
|
|
|
|
5 | 130 | 120 | 115 |
|
|
|
|
|
6 | 140 | 135 | 130 |
|
|
|
|
|
7 | 165 | 150 | 155 |
|
|
|
|
|
8 | 200 | 175 | 190 |
|
|
|
|
|
9 | 250 | 220 | 230 |
|
|
|
|
|
10 | 270 | 260 | 270 |
|
|
|
|
|
11 | 300 | 295 | 305 |
|
|
|
|
|
12 | 350 | 340 | 340 |
|
|
|
|
|
13 | 380 | 360 | 370 |
|
|
|
|
|
14 | 420 | 395 | 400 |
|
|
|
|
|
15 | 460 | 460 | 450 |