Question: Complete the capacity bill below based on the capacity bills approach Bill of capacity: A B Center Total Time / Unit Total Time / Unit

Complete the capacity bill below based on the capacity bills approach

Bill of capacity:

A B
Center Total Time / Unit Total Time / Unit
100 0.2 0.2
200 0.3 0.3
300 0.4 0.5
Total Time/ Unit 0.9 1.0

MPS:

Period
Product 1 2 3 4 5
A 10 10 10 20 20
B 20 20 10 20 10

Capacity Requirements Using Capacity Bills

Period
Center 1 2 3 4 5
100
200
300
Total required capacity