Question: Complete the capacity bill below based on the capacity bills approach Bill of capacity: A B Center Total Time / Unit Total Time / Unit
Complete the capacity bill below based on the capacity bills approach
Bill of capacity:
| A | B | |
| Center | Total Time / Unit | Total Time / Unit |
| 100 | 0.2 | 0.2 |
| 200 | 0.3 | 0.3 |
| 300 | 0.4 | 0.5 |
| Total Time/ Unit | 0.9 | 1.0 |
MPS:
| Period | |||||
| Product | 1 | 2 | 3 | 4 | 5 |
| A | 10 | 10 | 10 | 20 | 20 |
| B | 20 | 20 | 10 | 20 | 10 |
Capacity Requirements Using Capacity Bills
| Period | ||||||
| Center | 1 | 2 | 3 | 4 | 5 | |
| 100 | ||||||
| 200 | ||||||
| 300 | ||||||
| Total required capacity | ||||||