Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost Crash Cost /Day
A - 16 14 2000 4400
B - 14 9 1000 1800
C A 8 6 500 700
D A 5 4 600 1300
E B 4 2 1500 3000
F B 6 4 800 1600
G C 10 7 3000 4500
H D,E 15 10 5000 8000