Complete the MRP schedule for the product below. Product A Lot Size = 200 Safety Stock =
Fantastic news! We've Found the answer you've been seeking!
Question:
- Complete the MRP schedule for the product below.
Product A Lot Size = 200
Safety Stock = 50
Lead Time = 2 weeks Allocated = 100 In hand =500
WEEKS
1 | 2 | 3 | 4 | 5 | |
Gross requirement | 300 | 500 | 800 | 400 | |
Scheduled receipt | 100 | ||||
Available | |||||
Net requirements | |||||
Planned order receipts | |||||
Planned order releases |
- Product X has the structure given below.
X
P2 R3 S4
Q4 T3 V2
- If 50 units of product X has to be produced, compute the bill of materials.
ITEM | QUANTITY |
P | |
R | |
S | |
Q | |
T | |
V |
- Given the following lead times draw the time phased product structure for X
if delivery is desired in week 10 from now.
ITEM | LEAD TIME IN WEEKS |
X | 1 |
P | 2 |
Q | 1 |
R | 3 |
S | 2 |
T | 1 |
V | 2 |
1 2 3 4 5 6 7 8 9 10