Question: Complete the network diagram for activities A through L below. Insert durations and predecessor arrows, and then perform forward - pass, backward - pass, and

Complete the network diagram for activities A through L below. Insert durations and predecessor arrows, and then perform forward-pass, backward-pass, and float calculations. Answer the following questions based on the completed network
\\table[[ID:],[ES:,Duration:,LS:],[,,LF:],[EF:,,],[Total Float:,]]
\table[[ID:,D,],[ES:,Duration:,LS:],[,,LF:],[Iotal Float:,]]a. What is the critical path?
b. What is the overall duration of the project?
c. If Activity C, Rough-In Plumbing, took two extra days to complete, how much longer would the overall duration be?
d. If Activity I, Install Plumbing Fixtures, took six extra days to complete, how much longer would the overall duration be?
e. If Activity D, Rough-In HVAC, took four extra days to complete, Activity J, Install and Test HVAC System, took three extra days to complete, and Activity G, Finish and Paint Drywall, took two less days to complete, how much longer would the overall duration be?table[[Activitios Information],[Activity,Description],[A,Install Metal Stud Walls,12,],[B,Rough-In Electrical,8,Predecessors],[C,Rough-In Plumbing,9,A],[D,Rough-In HVAC,7,A],[E,Inspections,0,A],[F,Install Drywall,B, C, D,],[G,Finish and Paint Drywall,9,E],[H,Install Electrical Fixtures,1,F],[I,Install Plumbing Fixtures,3,G],[J,Install and Test HVAC System,6,G],[K,Punch List,3,G],[L,Closeout,H, I, J,,],[,,2,K]
Complete the network diagram for activities A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!