Question: Complete the network diagram for activities A through L below. Insert durations and predecessor arrows, and then perform forward - pass, backward - pass, and
Complete the network diagram for activities A through L below. Insert durations and predecessor arrows, and then perform forwardpass, backwardpass, and float calculations. Answer the following questions based on the completed network
tableID:ES:Duration:,LS:LF:EF:Total Float:,
tableID:DES:Duration:,LS:LF:Iotal Float:,a What is the critical path?
b What is the overall duration of the project?
c If Activity C RoughIn Plumbing, took two extra days to complete, how much longer would the overall duration be
d If Activity I, Install Plumbing Fixtures, took six extra days to complete, how much longer would the overall duration be
e If Activity D RoughIn HVAC, took four extra days to complete, Activity J Install and Test HVAC System, took three extra days to complete, and Activity G Finish and Paint Drywall, took two less days to complete, how much longer would the overall duration betableActivitios InformationActivityDescriptionAInstall Metal Stud Walls,BRoughIn Electrical,PredecessorsCRoughIn Plumbing,ADRoughIn HVAC,AEInspections,AFInstall Drywall,B C DGFinish and Paint Drywall,EHInstall Electrical Fixtures,FIInstall Plumbing Fixtures,GJInstall and Test HVAC System,GKPunch List,GLCloseout,H I, JK
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock