Question: Complete the resource loading chart below. ID RES DUR ES LF SL 0 - 1 - 2 - 3 - 4 - 5 - 6

Complete the resource loading chart below.

ID RES DUR ES LF SL 0 - 1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14
A 2 4 0 6 2
B 3 6 0 6 0
C 3 3 4 11 4
D 2 5 6 11 0
E 1 4 6 11 1
F 3 3 11 14 0
Total resource load 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Considering your computations in the previous question, what is the project's critical path?

Considering your computations in the previous question, what is the maximum number of resources required on the project?