Question: Compute and Estimate At Completion ( EAC ) and Variance At Completion ( VAC ) if SPI and CPI both influence the project work when

Compute and Estimate At Completion (EAC) and Variance At Completion (VAC) if SPI and CPI both influence the project work when variables given are as follows:
Budget At Completion (BAC)=30,000- rupees
Earned Value (EV)=15,000- rupees
Planned Value (PV)=12,000- rupees
Actual Cost (AC)=18,000- rupees
 Compute and Estimate At Completion (EAC) and Variance At Completion (VAC)