Question: Problem# 1 : Compute Estimate At Completion ( EAC ) and Variance At Completion ( VAC ) if both SPI and CPI influence the project

Problem#1:
Compute Estimate At Completion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given variables are
Budget At Completion (BAC)=$22,000
Earned Value (EV)= $13,000
Planned Value (PV)=$14,000
Actual Cost (AC)=$15,000
Problem#2:
For the following project calculate SV, CV, SPI, and CPI at the end of second month.
\table[[Month,1,2,3,4],[Planned Value,?bar()11,10,000,?bar()6,00,000,?bar()25,00,000,?bar()8,00,000
 Problem#1: Compute Estimate At Completion (EAC) and Variance At Completion (VAC)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!