Question: Compute Estimate at completion (EAC) and Variance at Completion (VAC) if both SPI and CPI influence the project work when given variables are Budget at
Compute Estimate at completion (EAC) and Variance at Completion (VAC) if both SPI and CPI influence the project work when given variables are
Budget at Completion = $22000 Earned Value = $13000 Planned Value = $14000 Actual Cost = $15000 Comment on the status of the project.