Question: . Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of

. Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 440 minutes per day, two 10-minute breaks, and an hour for lunch. There are two shift per day. The service system must process 90 jobs a day