Question: Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 440
Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 440 minutes per day, two 10-minute breaks, and an hour for lunch. The service system must process 90 jobs a day.
Step by Step Solution
3.38 Rating (170 Votes )
There are 3 Steps involved in it
Given Total time per shift 440 minutes There is 1 shift and workers are given two 10minute ... View full answer