Question: Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students. Activity ID
Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students.
| Activity | ID | Immediate Predecessor | Time (Wks) |
| Design Laptop | A | 21 | |
| Build Prototype | B | A | 5 |
| Evaluate Design | C | A | 7 |
| Test Prototype | D | B | 2 |
| Write Manual | E | C, D | 5 |
| Prep Production | F | C, D | 8 |
| Test Production | G | E, F | 2 |
a) Draw the project network.
b) Determine the critical path(s).
| ID | Time | ES | EF | LS | LF | TS | CP |
| A | 21 |
|
|
|
|
|
|
| B | 5 |
|
|
|
|
|
|
| C | 7 |
|
|
|
|
|
|
| D | 2 |
|
|
|
|
|
|
| E | 5 |
|
|
|
|
|
|
| F | 8 |
|
|
|
|
|
|
| G | 2 |
|
|
|
|
|
|
c) From the following information, determine the cost to crash the project to the shortest possible duration.
| Activity | ID | Immediate Predecessor | Time (Wks) | Min Time | Per Week Crash Cost |
| Design Laptop | A | 21 | 18 | $200 | |
| Build Prototype | B | A | 5 | 3 | $100 |
| Evaluate Design | C | A | 7 | 5 | $250 |
| Test Prototype | D | B | 2 | 1 | $300 |
| Write Manual | E | C, D | 5 | 5 | NA |
| Prep Production | F | C, D | 8 | 6 | $150 |
| Test Production | G | E, F | 2 | 1 | $300 |
|
|
|
|
| Crash | Cost | Total |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|