Question: Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students. Activity ID

Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students.

Activity

ID

Immediate Predecessor

Time (Wks)

Design Laptop

A

21

Build Prototype

B

A

5

Evaluate Design

C

A

7

Test Prototype

D

B

2

Write Manual

E

C, D

5

Prep Production

F

C, D

8

Test Production

G

E, F

2

a) Draw the project network.

b) Determine the critical path(s).

ID

Time

ES

EF

LS

LF

TS

CP

A

21

B

5

C

7

D

2

E

5

F

8

G

2

c) From the following information, determine the cost to crash the project to the shortest possible duration.

Activity

ID

Immediate Predecessor

Time (Wks)

Min Time

Per Week Crash Cost

Design Laptop

A

21

18

$200

Build Prototype

B

A

5

3

$100

Evaluate Design

C

A

7

5

$250

Test Prototype

D

B

2

1

$300

Write Manual

E

C, D

5

5

NA

Prep Production

F

C, D

8

6

$150

Test Production

G

E, F

2

1

$300

Crash

Cost

Total

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!