Question: Computing the duration of the network after all logic is completed and all time estimates are included, requires a forward and a backward pass resulting

Computing the duration of the network after all logic is completed and all time estimates are included, requires a forward and a backward "pass" resulting in:
New logic for the schedule if it exceeded the desired time duration
A sort of all activities into a forward group and a backward group
Identification of float on each activity, and the critical path
Separating the critical path from the non-critical path activities in the network