Question: Consider a construction project with 7 activities as shown in the table below. The predecessors of each activity and the duration of the activities are
Consider a construction project with 7 activities as shown in the table below. The predecessors of each activity and the duration of the activities are given. The number of cranes (consider it as a resource) required by each activity is also listed. The organization has only 6 cranes available with them