Question: Consider a continuous review inventory system with a lead time of two weeks. If the standard deviation of demand during lead time is 212.132 and

Consider a continuous review inventory system with a lead time of two weeks. If the standard deviation of demand during lead time is 212.132 and the desired order-cycle service level is 86%, what should the safety stock equal?

Group of answer choices

115

182

229

171

458