Question: Consider a cost plus incentive fee contract where the expected cost is $14,500,000, the fee to the supplier is $1,500,000, and the share formula is

  1. Consider a "cost plus incentive fee" contract where the expected cost is $14,500,000, the fee to the supplier is $1,500,000, and the share formula is 90/10. Assume the final cost of the project is actually $12,580,000. What is the total payment to the supplier?