Question: Consider a line that makes two different astronomical digital cameras. The TS - 7 costs Consider a line that makes two different astronomical digital cameras.
Consider a line that makes two different astronomical digital cameras. The TS costs
Consider a line that makes two different astronomical digital cameras. The TS costs
$ while the TS which uses a much larger chip, costs $ Most of the cost of the
$ while the TS which uses a much larger chip, costs $ Most of the cost of the
cameras is due to the cost of the chip. In manufacturing, both go through the same three
cameras is due to the cost of the chip.
steps but take different amounts of time. The capacities for the TS are seven, five, and six
per day at workstations and respectively that is if we run exclusively TS
product Similarly, capacity for the TS is six per day at all stations again assuming we
run only TS Five percent of TS units must be reworked, which requires them to go
back through all three stations a second time process times are the same as those for the
first pass Reworked jobs never make a third pass through the line. There is no rework for
the TS Demand is three per day for the TS and one per day for the TS The average
inventory level of chips is for the TS and five for the TS Cycle time for both
cameras is four days, while the raw process time with no detractors is onehalf a day.
Cameras are made to stock and sold from finished goods inventory. Average finished goods
inventory is four units of the TS and one unit of the TS while the average backorder
level is for TS and for TS
a Compute throughput THi for each station for each product.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
