Question: Consider a process consisting of three resources: ResourceProcessing Time [ Min . / Unit ] Number of Workers 1 1 0 2 2 6 1
Consider a process consisting of three resources:
ResourceProcessing Time MinUnitNumber of Workers
a What is the bottleneck?
b What is the process capacity?
c What is the flow rate if demand is eight units per hour?
d What is the utilization of each resource if demand is eight units per hour? Round the answers to decimal places.