Question: Consider a process in which all customers go through the first two steps, B1 and B2, each staffed by one worker. Then customer can be

Consider a process in which all customers go through the first two steps, B1 and B2, each staffed by one worker. Then customer can be served by either of the two servers at step B3. The two servers work at different speed. The process ends for all customers at step B4 with one worker. The numbers in parentheses indicate the minutes it takes that activity/worker to process a customer.

B1(7)-B2(8)(10)B3-a(10)B3-b(15)B4-(12)

x y grapha. How long does it take the average customer to complete this process?

nothing

minutes. (Enter your response rounded to one decimal place.)b. What is the total capacity of step B3?

nothing

customers per hour.c. What single activity is the bottleneck for the entire process?

Bnothing

d. How many customers can this process serve in an hour?

nothing

customers per hour. (Enter your response as an integer.)

Enter your answer in each of the answer boxes.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!