Question: Consider a process with lower process control limit as 1.338 and upper process controllimit as 1.342. The lower specification limit is 1.335 and the upper

Consider a process with lower process control
Consider a process with lower process control limit as 1.338 and upper process controllimit as 1.342. The lower specification limit is 1.335 and the upper specification limit is 1.345. Utilizing the information provided, is the process is capable of meeting design specifications? No Cannot say from the information provided. Yes None of the above