Question: Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 4 B none 6 C A 9 D A 7
Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks)
A none 4 B none 6 C A 9 D A 7 E B 4 F D, E 5 G F 4
a) Draw an AON diagram for the project.
(b) What is the project duration?
(c) Show the two-pass procedure on the AON diagram to find the critical path.
(d) What is the slack for each activity?