Question: Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 3 B A 5 C B 4 D B 5

Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 3 B A 5 C B 4 D B 5 E C 3 F D 8 G E, F 3

(a) Draw an AON diagram for the project.

(b) What is the project duration?

(c) Show the two-pass procedure on the AON diagram to find the critical path.

(d) What is the slack for each activity?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!