Question: Consider a project with four activities: A, B, C and D. Assume A can be started as soon as the project is kicked off. B

Consider a project with four activities: A, B, C and D. Assume A can be started as soon as the project is kicked off. B and C can both start as soon as A is completed (B and C can happen simultaneously). D can start as soon as both B and C are completed. Which of the following choices is the correct collection of immediate precedence relationships in the project network?

a.

A--> B, B --> C, C--> D

b.

A-->B, A--->C, B--->C, C-->D

c.

A-->B, A--->C, B--->C, B-->D, C--->D

d.

A-->B, A--->C, B--->D, C--->D

Step by Step Solution

There are 3 Steps involved in it