Question: A project has four activities - A, B, C and D, - that take 4, 3, 6 and 7 days, respectively. Activities A and B
A project has four activities - A, B, C and D, - that take 4, 3, 6 and 7 days, respectively. Activities A and B can start immediately. Activity C requires the completion of both A and B, and activity D requires the completion of activity C. What is the total completion time for the project?
| 3 days | ||
| 17 days | ||
| 20 days | ||
| Cannot be tell, not enough information provided |