Question: A project has four activities - A, B, C and D, - that take 4, 3, 6 and 7 days, respectively. Activities A and B

A project has four activities - A, B, C and D, - that take 4, 3, 6 and 7 days, respectively. Activities A and B can start immediately. Activity C requires the completion of both A and B, and activity D requires the completion of activity C. What is the total completion time for the project?

3 days

17 days

20 days

Cannot be tell, not enough information provided