Question: Consider a project with four activities: A & C and D. Assume A can be started as soon as the project is kicked off. B

Consider a project with four activities: A & C and D. Assume A can be started as soon as the project is kicked off. B can start as soon as A is completed ( and D can start as soon as B is completed. (C and D can happen simultaneously). Normal Duration (in daps. A = 4 B =5, C= 6 and D =7. The deadline is 13 days from the start, every day of delay beyond this deadline mil costs the company 5225 (per day) The duration of each activity can be reduced by one day by incurring the (bilbwing crashing coots. A = 200 Sid3, B= 300 5/day, C= 50 S day and D = 100 S/day. No activities duration can be reduced by more than one day. What should the project manager do according to the greedy method?

a.Crash A and D by one day each. b.Crash A, B, C, and D by one day each

c. Crash A, C, and D by one-day exch d.Cash A and C by one day each.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!