Question: Consider a project with the following activity paths for the network: A-B-E-G (40 days) A-C-D-J (39 days) A-H-J (36 days) If the duration of activity

Consider a project with the following activity paths for the network:

A-B-E-G (40 days)

A-C-D-J (39 days)

A-H-J (36 days)

If the duration of activity J is increased by 6 days, by how many days will the duration of the project be increased?

Consider a project with the following activity paths for the network:

A-B-E-G (25 days)

A-C-D-J (27 days)

A-H-J (24 days)

If activity D is shortened by 4 days, by how many days will the duration of the project be shortened?