Question: Consider a project with the following activity paths for the network: A-B-E-G(42days)A-C-D-J(38days)A-H-J(36days) If the duration of activity J is increased by 7 days, by how
Consider a project with the following activity paths for the network: A-B-E-G(42days)A-C-D-J(38days)A-H-J(36days) If the duration of activity J is increased by 7 days, by how many days will the duration of the project be increased