Question: Consider a project with the following dependency matrix and activity processing times. 1- Calculate Earliest Project Completion Time. 2- What is the critical path? 3-
Consider a project with the following dependency matrix and activity processing times.
1- Calculate Earliest Project Completion Time.
2- What is the critical path?
3- What if B takes 2 days longer than originally planned, how much would the PCT be delayed?