Question: Consider the project with the following dependency matrix. Activity Predecessor Activity Times (Days) 1 2 2 1 5 3 2 7 4 2 3 5

Consider the project with the following dependency matrix.

Activity Predecessor Activity Times (Days)
1 2
2 1 5
3 2 7
4 2 3
5 2 4
6 4,5 6
7 3,6 3
8 6,7 8

a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT.

b) Draw a Gantt chart for this project including slack times (Optional: utilize commercial software if possible).