Question: 3. Problem (Ch. 19, Project Management) Consider the project with the following dependency matrix. Predecessor Activity Time (Days) 2 5 Activity 1 2 3 4

3. Problem (Ch. 19, Project Management) Consider

3. Problem (Ch. 19, Project Management) Consider the project with the following dependency matrix. Predecessor Activity Time (Days) 2 5 Activity 1 2 3 4 5 7 3 1 2 2 2 4,5 3,6 6,7 4 6 6 7 3 8 8 a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT. b) Draw a Gantt chart for this project including slack times

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!