Question: Consider a project with the following information. Construct the project activity network using the: Activity Duration Predecessors A 3 - B 5 A C 7

Consider a project with the following information. Construct the project activity network using the:

Activity Duration Predecessors
A 3 -
B 5 A
C 7 A
D 3 B, C
E 5 B
F 4 D
G 2 C
H 5 E, F, G

(a) Activity On Arrow (AOA) methodology and appropriately label each node and arrow. Identify all dummy activities required to complete the network.

(b) Also identify critical path using forward pass and backward pass methods and show activities slack.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!