Question: Consider a project with the following information. Construct the project activity network using AOA methodology and label each node and arrow appropriately. Identify all dummy
.png)
Activity Duration Predecessors B, C E, F, G Activity Duration ES EF LS LF Slack 10 2 10 3 1013 10 13 13 12 174 10 12 15 17 5 17 22 1722
Step by Step Solution
3.57 Rating (178 Votes )
There are 3 Steps involved in it
1 0 a 3 2 3 3 ... View full answer