Question: Consider a sequential process with 3 stations. The processing time ( minutes per unit ) and number of employees at each station are as follows:

Consider a sequential process with 3 stations. The processing time (minutes per unit) and number of employees at each station are as follows:
\table[[,Processing time/unit,Number of Employees],[Station A:,4 minutes,1 employee],[Station B:,2 minutes,2 employees],[Station C:,5 minutes,1 employee]]
Where is the bottleneck?
Station C
Station B
Station A and B
Station B and C
Station A