Question: Consider a serial production process with 3 stations. Station A1 produces a component. Station A2 produces another component. Stations A1 and A2 work in parallel.
Consider a serial production process with 3 stations. Station A1 produces a component. Station A2 produces another component. Stations A1 and A2 work in parallel. The components produced at A1 and A2 are then passed to Station B that assembles them. The assembly at Station B requires one unit from A1 and one unit from A2. Station A1 can complete the work of one unit in 7 minutes. Work at Station A2 takes 6 minutes per unit, and work at Station B takes 9 minutes per unit. No work in process is allowed to build between stations.
a, Which station is the bottleneck of this serial process?
Station A1
Station A2
Station B
All stations are the bottleneck in this process.
The bottleneck cannot be identified with the available information.
b, What is the cycle time of the process
7 minutes
9 minutes
16 minutes
22 minutes
Cannot be computed with the available information
c,
What is the flow time of a unit in this process if there are no delays
9 minutes
15 minutes
16 minutes
22 minutes
All of the above
d,
What is the hourly throughput rate (capacity or output) of the process if the throughput of station B doubles by hiring additional workers
6.67 units per hour
7 units per hour
8.57 units per hour
10 units per hour
13.33 units per hour
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts